Yaroslavl Region

Yaroslavl CHPP-2 expansion by installing gas-turbine unit GTE-160 and waste-heat boiler on the existing turbine PT-60-130/13

Project implementation provides:

  1. Dismantlement of the steam boilers of the first priority for installation GTE-160 and waste-heat boiler;
  2. Installation of the GTE-160 unit with waste-heat boiler for 9 MPa and 500-535°С steam conditions;
  3. Booster compression station installation;
  4. Steam turbine PT-60-130 reconstruction, switching to pulled-down parameters;
  5. Construction of open distribution unit ORU-220kV on the place of dismantlement cells 1 and 2 of the existing ORU-110kV. Construction of VL 220kV from CHPP along the dismantled VL 110kV VL#156
  6. Construction costs 2 171 million rubles.

Technical and economic performance before and after project implementation

Year Fuel consumption rate for produced electricity, g/KWh Fuel consumption rate for generated heat, kg/Gcal Power supply from bus lines, in thous. KWh Heat supply from collectors, in thous. Gcal
2006 375,6 144,9 734 329 1 880 011
2010 262,3 135,3 2 215 352 3 419 000